Masangano-Fisenge-Luanshya Road Works Reach 10KM in Asphalt Surfacing

Must read

The Lusaka-Ndola Dual Carriageway Project, which includes the construction of the 45-kilometre Masangano-Fisenge-Luanshya Road on the Copperbelt, is making significant strides.

Recent updates indicate that the Masangano-Fisenge-Luanshya Road section has achieved approximately 70% completion. Notably, 10 kilometres of asphalt surfacing have been completed, and substantial progress has been made on drainage structures and the Toll Plaza.

Completion of the Masangano-Fisenge-Luanshya Road is anticipated by December 31, 2024.

Credit: RDA