The Lusaka-Ndola dual carriageway road construction works are progressing swiftly.

A government update states that 32km of the Luanshya-Masangano-Fisenge portion has been cleared and the roadbed prepared.

Half the work needed on the drainage structures has been done as the developer progresses work on the remaining one structure out of three.

Work is going on at four different sites along the road.

The 45km Luanshya-Masangano-Fisenge portion is part of the 327km Lusaka-Ndola road, which is being updated to dual carriage.